Northern Bangladesh Integrated Development Project (NOBIDEP)

Project Annual Work Plan


Local Government Engineering Department

Annual Work Plan 2018-19





Name of the Project: Northern Bangladesh Integrated Development Project (NOBIDEP)
Duration : March 2013 - June 2019






Approved Estimated Cost ( Lakh Taka)   Total: 270594.00  GoB : 57837.00  Project Aid: 212757.00
Cummulative Expenditure upto June 2018 ( Lakh Taka)



2018-19 FY ADP Allocation ( Lakh Taka )   Total: 39000.00  GoB : 5000.00  Project Aid: 34000.00
The Project is targeted for completion by this year Yes  


The Project will be completed by this year 
  No


Allocation needs changes in RADP
Yes  



Name of Components

Targeted Expenditure up to July 2018

Targeted Expenditure up to August 2018

Targeted Expenditure up to September 2018

 

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

 

Total

Taka

Project Aid

Total

Taka

Project Aid

Total

Taka

Project Aid

1

2

3

4

5

6

7

8

9

10

11

12

13

Revenue Components

 

 

 

 

 

 

 

 

 

 

 

 

Salary of Officers

 

25.00

25.00

 

 

25.00

25.00

 

 

25.00

25.00

 

Salary of Staffs

 

11.00

11.00

 

 

11.00

11.00

 

 

11.00

11.00

 

Allowances

 

25.00

25.00

 

 

25.00

25.00

 

 

25.00

25.00

 

Supplies & Services

 

275.00

75.00

200.00

 

325.00

125.00

200.00

 

350.00

200.00

150.00

Repair, Maintenance & Rehabilitation

 

2.00

2.00

 

 

2.00

2.00

 

 

4.00

4.00

 

Sub-Total : A

 

338.00

138.00

200.00

 

388.00

188.00

200.00

 

415.00

265.00

150.00

Capital  Components

 

 

 

 

 

 

 

 

 

 

 

 

Acquisition of Asset

 

 

 

 

 

 

 

 

 

5.00

5.00

0.00

UZR Improvement

 

 

 

 

2

200.00

 

200.00

3

300.00

 

300.00

UNR Improvement

 

 

 

 

3

300.00

 

300.00

3

300.00

 

300.00

GC Improvement

 

 

 

 

 

 

 

 

 

 

 

 

RM Improvement

 

 

 

 

 

 

 

 

 

 

 

 

Ghat Improvement

 

 

 

 

 

 

 

 

 

 

 

 

Upazila & Union Road Maintenance (By LCS)

8

35.00

 

35.00

8

35.00

 

35.00

8

40.00

 

40.00

UZR Rehabilitation

 

 

 

 

 

 

 

 

 

 

 

0.00

Pourashava Infrastructure Improvement

5

400.00

 

400.00

6.00

500.00

 

500.00

6

600.00

 

600.00

CD & VAT

 

 

 

 

 

 

 

 

 

 

 

 

Sub-Total : B

 

435.00

0.00

435.00

 

1035.00

0.00

1035.00

 

1245.00

5.00

1240.00

Grand Total

3%

773.00

138.00

635.00

4%

1423.00

188.00

1235.00

6%

1660.00

270.00

1390.00

( Sub-A+ Sub-B)














Name of Components

Targeted Expenditure up to Ocober 2018

Targeted Expenditure up to November 2018

Targeted Expenditure up to December 2018

 

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

 

Total

Taka

Project Aid

Total

Taka

Project Aid

Total

Taka

Project Aid

1

14

15

16

17

18

19

20

21

22

23

24

25

Revenue Components

 

 

 

 

 

 

 

 

 

 

 

 

Salary of Officers

 

25.00

25.00

 

 

25.00

25.00

 

 

25.00

25.00

 

Salary of Staffs

 

11.00

11.00

 

 

11.00

11.00

 

 

12.00

12.00

 

Allowances

 

25.00

25.00

 

 

25.00

25.00

 

 

25.00

25.00

 

Supplies & Services

 

450.00

250.00

200.00

 

500.00

250.00

250.00

 

550.00

350.00

200.00

Repair, Maintenance & Rehabilitation

 

4.00

4.00

 

 

4.00

4.00

 

 

6.00

6.00

 

Sub-Total : A

 

515.00

315.00

200.00

 

565.00

315.00

250.00

 

618.00

418.00

200.00

Capital  Components

 

 

 

 

 

 

 

 

 

 

 

 

Acquisition of Asset

 

5.00

0.00

5.00

 

5.00

0.00

5.00

 

5.00

5.00

0.00

UZR Improvement

5

500.00

 

500.00

7

800.00

 

800.00

8

1000.00

 

1000.00

UNR Improvement

5

500.00

 

500.00

5

500.00

 

500.00

7

600.00

 

600.00

GC Improvement

 

 

 

 

1

50.00

 

50.00

2

150.00

 

150.00

RM Improvement

 

 

 

 

 

 

 

 

1

75.00

 

75.00

Ghat Improvement

 

 

 

 

 

 

 

 

1

10.00

 

10.00

Upazila & Union Road Maintenance (By LCS)

10

40.00

 

40.00

10

40.00

 

40.00

10

40.00

 

40.00

UZR Rehabilitation

2

150.00

 

150.00

2

250.00

 

250.00

2

300.00

 

300.00

Pourashava Infrastructure Improvement

10

850.00

 

850.00

13

1050.00

 

1050.00

15

1200.00

 

1200.00

CD & VAT

 

 

 

 

 

 

 

 

 

 

 

 

Sub-Total : B

 

2045.00

0.00

2045.00

 

2695.00

0.00

2695.00

 

3380.00

5.00

3375.00

Grand Total

8%

2560.00

315.00

2245.00

9%

3260.00

315.00

2945.00

12%

3998.00

423.00

3575.00

( Sub-A+ Sub-B)














Name of Components

Targeted Expenditure up to January 2018

Targeted Expenditure up to February 2018

Targeted Expenditure up to March 2018

Targeted Expenditure up to April 2018

 

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

 

Total

Taka

Project Aid

Total

Taka

Project Aid

Total

Taka

Project Aid

Total

Taka

Project Aid

1

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

Revenue Components

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Salary of Officers

 

25.00

25.00

 

 

25.00

25.00

 

 

25.00

25.00

 

 

25.00

25.00

 

Salary of Staffs

 

11.00

11.00

 

 

11.00

11.00

 

 

11.00

11.00

 

 

11.00

11.00

 

Allowances

 

25.00

25.00

 

 

25.00

25.00

 

 

25.00

25.00

 

 

25.00

25.00

 

Supplies & Services

 

500.00

300.00

200.00

 

500.00

350.00

150.00

 

550.00

350.00

200.00

 

500.00

350.00

150.00

Repair, Maintenance & Rehabilitation

 

3.00

3.00

 

 

3.00

3.00

 

 

3.00

3.00

 

 

3.00

3.00

 

Sub-Total : A

 

564.00

364.00

200.00

 

564.00

414.00

150.00

 

614.00

414.00

200.00

 

564.00

414.00

150.00

Capital  Components

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Acquisition of Asset

 

 

 

 

 

5.00

0.00

5.00

 

5.00

0.00

5.00

 

5.00

5.00

0.00

UZR Improvement

5

800.00

 

800.00

10

1200.00

 

1200.00

15

2000.00

 

2000.00

10

1500.00

 

1500.00

UNR Improvement

13

1200.00

 

1200.00

15

1500.00

 

1500.00

17

1500.00

 

1500.00

15

1300.00

 

1300.00

GC Improvement

2

150.00

 

150.00

1

100.00

 

100.00

1

150.00

 

150.00

1

150.00

 

150.00

RM Improvement

2

100.00

 

100.00

2

150.00

 

150.00

3

200.00

 

200.00

3

175.00

 

175.00

Ghat Improvement

 

 

 

 

 

 

 

 

 

 

 

0.00

 

 

 

0.00

Upazila & Union Road Maintenance (By LCS)

10

40.00

 

40.00

10

40.00

 

40.00

8

35.00

 

35.00

6

35.00

 

35.00

UZR Rehabilitation

 

50.00

 

50.00

 

 

 

0.00

 

 

 

0.00

 

 

 

0.00

Pourashava Infrastructure Improvement

10

800.00

 

800.00

10

800.00

 

800.00

9

740.00

 

740.00

10

850.00

 

850.00

CD & VAT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Sub-Total : B

 

3140.00

0.00

3140.00

 

3795.00

0.00

3795.00

 

4630.00

0.00

4630.00

 

4015.00

5.00

4010.00

Grand Total

11%

3704.00

364.00

3340.00

12%

4359.00

414.00

3945.00

15%

5244.00

414.00

4830.00

12%

4579.00

419.00

4160.00

( Sub-A+ Sub-B)


















Name of Components

Targeted Expenditure up to May 2018

Targeted Expenditure up to June 2018

Total Targeted Expenditure

 

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

Physical Target
( No,  M, Man-Month, Km etc.)

Financialet Target
( Lakh Taka)

 

Total

Taka

Project Aid

Total

Taka

Project Aid

Total

Taka

Project Aid

1

42

43

44

45

46

47

48

49

50

51

52

53

Revenue Components

 

 

 

 

 

 

 

 

 

 

 

 

Salary of Officers

 

25.00

25.00

 

 

25.00

25.00

 

Man month

300.00

300.00

 

Salary of Staffs

 

11.00

11.00

 

 

13.00

13.00

 

Man month

135.00

135.00

 

Allowances

 

25.00

25.00

 

 

25.00

25.00

 

 

300.00

300.00

 

Supplies & Services

 

450.00

300.00

150.00

 

400.00

300.00

100.00

 

5350.00

3200.00

2150.00

Repair, Maintenance & Rehabilitation

 

5.00

5.00

 

 

6.00

6.00

 

 

45.00

45.00

 

Sub-Total : A

 

516.00

366.00

150.00

 

469.00

369.00

100.00

 

6130.00

3980.00

2150.00

Capital  Components

 

 

 

 

 

 

 

 

 

 

 

 

Acquisition of Asset

 

 

 

 

 

10.00

5.00

5.00

LS

45.00

20.00

25.00

UZR Improvement

10

1500.00

 

1500.00

 

1200.00

 

1200.00

75 KM

11000.00

0.00

11000.00

UNR Improvement

12

1000.00

 

1000.00

10

800.00

 

800.00

105 KM

9500.00

0.00

9500.00

GC Improvement

1

150.00

 

150.00

1

75.00

 

75.00

10

975.00

0.00

975.00

RM Improvement

1

100.00

 

100.00

 

50.00

 

50.00

12

850.00

0.00

850.00

Ghat Improvement

 

 

 

0.00

 

 

 

0.00

1 wU

10.00

0.00

10.00

Upazila & Union Road Maintenance (By LCS)

6

35.00

 

35.00

6

35.00

 

35.00

100KM

450.00

0.00

450.00

UZR Rehabilitation

 

 

 

0.00

 

 

 

0.00

6 KM

750.00

 

750.00

Pourashava Infrastructure Improvement

8

750.00

 

750.00

8

750.00

 

750.00

110 KM

9290.00

 

9290.00

CD & VAT

 

 

 

 

 

 

 

 

LS

0.00

0.00

0.00

Sub-Total : B

 

3535.00

0.00

3535.00

 

2920.00

5.00

2915.00

 

32870.00

20.00

32850.00

Grand Total

8%

4051.00

366.00

3685.00

 

3389.00

374.00

3015.00

 

39000.00

4000.00

35000.00

( Sub-A+ Sub-B)