Project Annual Work Plan

 







 Project Annual Work Plan (CUMCP)
SL NO. Name of Important Components (With quantity) Cost as per RDPP/ TPP (Tk. In Lakh) Achievement upto Last Dec /18 Unspent/unfinished balance against DPP target 
Financial  Physical Financial  Physical
 Total (% of the component)  Total (% of the component)
Taka   Taka  
1 2 3   4   5
1 Pay of Officers 111.08 78.24 70.44% 32.84 29.56%
2 Pay of Establishment 32.74 21.90 66.89% 10.84 33.11%
3 Allowances 109.84 84.33 76.78% 25.51 23.22%
4 Supplies and Services 294.35 240.21 81.61% 54.14 18.39%
5 Repair Maintenance and Rehabilitation 35.95 34.93 97.16% 0.54 1.50%
6 Acquisition of Assets 3337.81 767.64 23.00% 2569.48 76.98%
7 Land Acquisition 5031.79 1838.23 37% 2837.56 56.39%
8 Construction Works 112800.00 62405.00 55.32% 44339.38 39.31%
9 Physical Contingency 400.00 0.00 0.00% 400.00 100.00%
10 Price Contingency 200.00 0.00 0.00% 200.00 100.00%
  Grand Total : 122353.56 65470.48 53.51% 56883.08 46.49%