Infrastructure Improvement of Langalbandh Maha Ashtami Holy Bath Festival Project (LMAHBFP)

Menu
Project Office LGED
Infrastructure Improvement of Langalbandh Maha Ashtami Holy Bath Festival Project
Local Government Engineering Department (LGED)
RDEC Bhaban, Level-9 Agargaon, Sher-e-Bangla Nagar, Dhaka-1207

Project Annual Work Plan

7000

Civil Works

Unit

Qty.

Unit cost

Total cost  (Tk. In Lk.

7001

Land Development

cum

125000

0.004

500.00

7031

Road Widening/Development

km

5.50

120

660.00

7031

Construction of Culverts

m

75

7.5

562.50

7031

Footpath

m

2790

0.6

1674.00

7016

Construction/Widening of Ghat

m

180

8.5

1530.00

7016

Development of Car Parking

sqm

16728

0.06

1003.68

7016

One Dormitory for Pilgrims

sqm

1672.9

0.38

635.69

7016

Pilgrims Waiting Shed

Nos

6

50

300.00

7016

Public Toilet

Nos

15

40

600.00

7016

Deep Tube Well with pipe line

Nos

6

18.5

111.00

7016

Overhead Tank

Nos

6

10

60.00

7016

Changing Room

Nos

7

25

175.00

7016

Watch Tower

Nos

3

16

48.00

7016

Police Box

Nos

1

10

10.00

7016

CC Camera Stand

Nos

20

0.75

15.00

7016

Construction of Temples

Nos

5

40

200.00

7016

Temple Rehabilitation/Maintenance

Nos

12

15

180.00

7016

Garbage Clearing

LS

 

 

20.00

7016

Electric line & Pole shifting

LS

 

 

60.00

 

Sub total of Civil Wroks  =

 

 

 

8344.87