Greater Dhaka Rural Infrastructure Improvement Project-4 (2nd Revised) (GDP-4)

Project Annual Work Plan

8) Target and Achievement of the main Components of the Project :
In Lac
Sl. No. Work components as per RDPP (With quantity) Estimated Cost Target of the current year
Financial Physical (% of the component)
1 Development of  Upazilla Road(28.65 k.m.) 3029.94 492.00  4.65  k.m. (16.23%) 
2 Rehabilitation of Upazilla & Union Road(18.48  k.m.) 1653.64 403.00  4.50  k.m. (24.35%) 
3 Development of Union Road(78.37 k.m.)  7964.94 1016.00  10.00  k.m. (12.75%) 
4 Development of Village Road By RCC(78.61 k.m.) 14086.69 1375.00  8.50  k.m. (10.81%) 
5 Development of  Village Road By BC(479.95 k.m.) 41229.02 4465.06  71.94 k.m. (14.98%) 
6 Widening of  Upazilla/Union Road(6.13 k.m.) 829.49 134.75  2.60 k.m. (42.41%) 
7 Side Widening of  Village Road By BC(3.64 k.m.) 221.46 55.45  1.24  k.m. (33.79%) 
8 Slope Protection of Road (43208 s.m.) 717.74 77.00 4664 s.m.  (89.13%)
9 Maintenance of Upazilla Road(7.37 k.m.) 489.93 150.00 4.44 k.m.  (60.10%)
10 Maintenance of Union Road(16.63 k.m.) 1117.50 200.00 5.50 k.m.  (33.07%)
11 Maintenance of Village Road (17.18 k.m.) 595.58 110.00 1.93 k.m.  (52.50%)
12 Construction of Bridge On Upazilla , Union & Village Road(574.00 m.) 4630.52 1232.00 154 m.  (26.82%)
13 Construction of  Culvert On Upazilla , Union & Village Road(33.50 m.) 180.82          55.00 11 m. (32.83%)
14 Construction  of  RCC Drain On village Road(1545.00m) 281.96                  -                   -
15 Physical Contingency 371.75                  -                   -
16 Price Contingency 500.00                  -                   -
17 Tree Plantation (7.00 k.m.) 14.00                  - -
18 Jeep 91.00                  -                   -
19 Computer & Materials 4.20                  -                   -
20 Photocopier 3.00                  -                   -
21 Scanner 0.20                  -                   -
22 Furniture 2.00                  -                   -
23 Telephone Set 0.20                  -                   -
24 Others (Office Partition) 2.00                  -                   -
25 Pay of officer (4 Persons) 150.00 25.42 16.94%
26 Pay of Staff (2 Persons) 46.00 8.36 18.17%
27 Allowance 175.50 25.81 14.70%
28 Estublishment Expenditure 1220.40 154.4 12.34%
29 Internal Travel & Transfer 17.50 1.50 8.57%
30 Supply, Material & General Expenditure 46.00 7.00 15.21%
31 Printing & Stationary  40.00 7.00 17.50%
32 Repair & Maintenance 31.00 5.25 16.93%
    79744.00 10000.00