Major Component of the Project:
*Components
No. Name of the Components Physical Quantity
(nos/km/m.) Cost as per DPP
(Tk in Lakh)
A. Revenue Component :
1. Manpower(Officer) 5persons 192.00lakh
2. Manpower(Staff))3 persons 63.00lakh
2. Manpower Outsourcing 33persons 66.00
3. Supply & Services and Repairs, Maintenance & Rehabilitation LS 1283.00 lakh
B. Capital Component :
4. Transport (Picup+Jeep old)4 nos Costing of Jeep 1nos 90.86 Lakh + .Pickup 3nos 143.32lack
5. Computer with Accessories 28nosnos. 55.00 lakh
8. Tree Plantation 100 km 100.00
9. Land Acquisition/ Purchase: 10acre 1000lakh
Civil works
10 Market Development 20 nos 700.00lakh
11 Rural roads &Structures
(a) Imp. ofUpazila Road 22.00 km 1892.00 lakh
(b) Imp. ofUnion Road 53.00 km 3710.00 lakh
(c) Imp. OfVillage Road 810.00 km 56700.00 lakh
(d) Widening/Imp. Of Road by HBB 105.00 km. 5250.00 lakh