Greater Noakhali District Rural Infrastructure Development - 3rd Phase(2nd revised)

Project Annual Work Plan


Physical Annual Target of the Project (FY:2020-21):

                                                   (In lakh Taka)

Name of   Important Components

(With quantity)

 Cost as per DPP

 

 Target of  current year

(2020-21)

Financial

Physical

(1)

(2)

(5)

(6)

1. Improvement  of Upazila road (22 Km)

1892.00

172.00

 

2.00 km

 

2. Improvement  of Union road (53 Km)

3710.00

70000

 

10.00km

 

3. Improvement  of Village road (810 Km)

 56700.00

8245.00

117.79 km

 

4. Bridge on Upazila road (100 m)

800.00

0.00

 

0.00 m

 

5.Culvert on Upazila road (50 m)

250.60

0.00

 

0.00 m

 

6.Bridge  on Union road  (340 m)

2550.00

375.00

 

50.00 m

 

7.Culvert on Union road (108  m)

486.00

67.50

 

15.00 m

 

7.Bridge  on Village road  (1370 m)

9590.00

2100.00

 

300.00 m

 

8.Culvert  on Village road  (1179  m)

5305.00

225.00

 

50.00 m

 

2. School Connecting road (106  Km)

7420.00

70.00

 

1.00 km

 

2. Improvement  of HBB road (105 Km)

5250.00

300.00

 

6.00 km

 

9.  Widening & strengthening    (22 km)

1100.00

100.00

 

2.00 km

 

10.  Development of Growth Centre  (20 Nos)

700.00

105.00

 

3 nos.

 

11.Slope Protection  (4535 sq. m)

907.00

20.00

 

100.00 sq.m

 

12.  Maintenance of Rural Roads (380 km.)

11400.00

3000.00

 

100.00 km

 

 

Note: Current year physical targethave been made on the basis of ADP allocation against the project.