Second City Region Development Project (CRDP-2)

Project Documents

Sl. Title Download
1 Semi-Annual Social Safeguard Monitoring Report (July-december-2024)
2 Semi-Annual Environmental Monitoring Report (July-December-2024)
3 Social Monitoring Report (January-June-2024)
4 Semi-Annual Environmental Monitoring Report (January-June-2024)
5 Land Acquisition and Involuntary Resettlement Due Diligence Report (Drainage Improvement in Mongla Pourashava Package No. CRDP-II/LGED/MONGLA/NCB/2021/W-01))
6 Land Acquisition and Involuntary Resettlement Due Diligence Report (Dhaka Region Roads - Dhaka Region Roads (GCC) Package No. CRDP-II/LGED/GCC/NCB/2020/W-03)
7 Land Acquisition and Involuntary Resettlement Due Diligence Report (Drainage Improvement in Dhamrai Pourashava Package No. CRDP-II/LGED/DHAMRAI/NCB/2021/W-01))
8 Land Acquisition and Involuntary Resettlement Due Diligence Report (Drainage Improvement in Singair Pourashava Package No. CRDP-II/LGED/SINGAIR/NCB/2021/W-01)
9 Land Acquisition and Involuntary Resettlement Due Diligence Report (Drainage Improvement in Narsingdi Pourashava Package No. CRDP-II/LGED/NARSINGDI/NCB/2021/W-01))
10 Land Acquisition and Involuntary Resettlement Due Diligence Report (Drainage Improvement in Jhikargacha Pourashava Package No. CRDP-II/LGED/JHIKARGACHA/NCB/2021/W-01)
11 Land Acquisition and Involuntary Resettlement Due Diligence Report (Drainage Improvement in Sonargaon Pourashava Package No. CRDP-II/LGED/SONARGAON/NCB/2021/W-01)
12 Land Acquisition and Involuntary Resettlement Due Diligence Report (Drainage Improvement in Kanchon Pourashava Package No. CRDP-II/LGED/KANCHON/NCB/2021/W-01)
13 Land Acquisition and Involuntary Resettlement Due Diligence Report (Dhaka Region Roads - Araihazar Upazila,Package No. CRDPII/LGED/NARAYANGANJ/ARAIHAZAR/NCB/2021/W-06)
14 Semi Annual Social Safeguard Monitoring July - December 2023
15 Initial Environment Examination for Dhaka Region Roads (Package No.CRDP-II/LGED/DHAKA/SAVAR/NCB/2021/W-05)
16 Semi-Annual Environmental Monitoring Report (July-December-2023)
17 Initial Environment Examination for Dhaka Region Roads (Araihazar Upazila) (Package No. CRDP-II/LGED/NARAYANGANJ/ARAIHAZAR/NCB/2021/W-06)
18 Initial Environment Examination for Dhaka Region Roads (Rupganj Upazila) (Package No. CRDP-II/LGED/NARAYANGANJ/RUPGANJ/NCB/2021/W-04 )
19 Initial Environment Examination for Drainage Improvement in Manikganj Pourashava-Revised (Package No. CRDP-II/LGED//MANIKGANJ/NCB/2021/W-01)
20 Initial Environment Examination for Drainage Improvement in Nowapara Pourashava (Package No. CRDP-II/LGED/NOWAPARA/NCB/2021/W-01)
21 Initial Environment Examination for Drainage Improvement in Kanchan Pourashava (Package No. CRDP-II/LGED/KANCHAN/NCB/2021/W-01)
22 Initial Environment Examination for Drainage Improvement in Kaliakoir Pourashava (Package No. CRDP-II/LGED/KALIAKOIR/NCB/2021/W-01)
23 Initial Environment Examination for Drainage Improvement in Dhamrai Pourashava (Package No. CRDP-II/LGED/DHAMRAI/NCB/2021/W-01)
24 Initial Environment Examination for Drainage Improvement in Tarabo Pourashava (Package No. CRDP-II/LGED/TARABO/NCB/2021/W-01)
25 Initial Environment Examination for Drainage Improvement in Jashore Pourashava (Package No. CRDP-II/LGED/JASHORE/NCB/2021/W-01)
26 Initial Environment Examination for Drainage Improvement in Sonargaon Pourashava (Package No. CRDP-II/LGED/SONARGAON/NCB/2021/W-01)
27 Initial Environment Examination for Dhaka Region Roads (Package No.CRDP-II/LGED/GCC/NCB/2020/W-03)
28 Initial Environment Examination for Drainage Improvement in Narsingdi Pourashava (Package No. CRDP-II/LGED//NARSINGDI/NCB/2021/W-01)
29 Initial Environment Examination for Drainage Improvement in Mongla Pourashava (Package No. CRDP-II/LGED/MONGLA/NCB/2021/W-01)
30 Initial Environment Examination for Drainage Improvement in Singair Pourashava (Package No. CRDP-II/LGED/SINGAIR/NCB/2021/W-01)
31 Initial Environment Examination for Drainage Improvement in Jhikargacha Pourashava (Package No. CRDP-II/LGED/JHIKORGACHA/NCB/2021/W-01)
32 Annual Procurement Plan (Goods and Services) for the FY 2022-23
33 Resettlement Plan (Savar-W-05_June-2022)
34 Semi-Annual Social Monitoring Report (Janu-June-2022)
35 Land Acquisition and Involuntary Resettlement Due Diligence Report (Dhaka Region Roads -Dhaka Region Roads (Araihazar Upazila) Package No. CRDPII/LGED/NARAYANGANJ/ARAIHAZAR/NCB/2021/W-05)
36 Initial Environmental Examination for Dhaka Region Roads (Savar Upazila-W-07Dhaka Region Roads (Savar Upazila-Package No. CRDP-II/LGED/DHAKA/SAVAR/NCB/2021/W-07
37 Initial Environmental Examination for Dhaka Region Roads (Dhaka Region Roads (Araihazar Upazila) Package No. CRDP-II/LGED/NARAYANGANJ/ARAIHAZAR/NCB/2021/W-05)
38 Land Acquisition and Involuntary Resettlement Due Diligence Report (Drainage Improvement in Kaliakoir Pourashava Package No. CRDP-II/LGED/KALIAKOIR/NCB/2021/W-01)
39 Land Acquisition and Involuntary Resettlement Due Diligence Report (Improvement of Drainage in Jashore Pourashavas-Package No. CRDP-II/LGED/JASHORE/NCB/2021/ W-01)
40 Land Acquisition and Involuntary Resettlement Due Diligence Report (Dhaka Region Roads -Drainage Improvement in Chalna Pourashava- Package No. CRDPII/LGED/CHALNA/NCB/2021/W-01))
41 Resettlement Plan (Bridge Construction at Chainage 4885 of Kanchan GC - Sorankhali bazar Chanpara RHD road - Package No. CRDP II/LGED/NARAYANGANJ/RUPGANJ/NCB/2018/W-02)
42 Land Acquisition and Involuntary Resettlement Due Diligence Report (Dhaka Region Roads - Araihazar Upazila,Package No. CRDPII/LGED/NARAYANGANJ/ARAIHAZAR/NCB/2021/W-04)
43 Land Acquisition and Involuntary Resettlement Due Diligence Report (Manikganj Pourashava, Package No.CRDP-II/LGED/MANIKGANJ/NCB/2021/W-01)
44 Resettlement Plan (Package No. CRDP-II/LGED/DHAKA/SAVAR/NCB/2021/W-05-Savar Pourashava)
45 Semi-annual Environmental Monitoring Report (January-June-2022)
46 Land Acquisition and Involuntary Resettlement Due Diligence Report (Drainage Improvement in Tarabo Pourashava-Package-W01)
47 Initial Environmental Examination for Drainage Improvement in Chalna Pourashava
48 Initial Environmental Examination for Dhaka Region Roads (Savar Upazila-W-06)
49 Semi-annual Environmental Monitoring Report (July-December 2021)
50 Semi-annual Social Monitoring Report (July - December 2021)
51 Semi-annual Environmental Monitoring Report (January-June-2021)
52 Semi-Annual Social Safeguard Monitoring Report (January - June 2021)
53 Semi-annual Environmental Monitoring Report (July-December-2020)
54 Semi-annual Social Monitoring Report (July-December -2020)
55 Initial Environmental Examination for Dhaka Region Roads (Araihazar Upazila-W-05)
56 Initial Environmental Examination for Dhaka Region Roads (Savar Upazila-W-07)
57 Contract Award Notice (Consultancy Service) for TAPP on ISWMIP
58 Dhaka Region Roads (Savar Upazila) _W04
59 Dhaka Region Roads (Araihazar Upazila-W03)
60 Semi-Annual Environmental Monitoring Report (Nov 2019 - June 2020)
61 Semi Annual Social Safeguard Monitoring July - December 2023
62 Land Acquisition and Involuntary Resettlement Due Diligence Report for Dhaka Region Roads (Gazipur City Corporation_GCC-W02)
63 Land Acquisition and Involuntary Resettlement Due Diligence Report for Dhaka Region Roads (Araihazar Upazila-W03)
64 Land Acquisition and Involuntary Resettlement Due Diligence Report for Dhaka Region Roads (Savar Pourashava-W01)
65 Land Acquisition and Involuntary Resettlement Due Diligence Report for Dhaka Region Roads (Savar Upazila-W04)
66 Land Acquisition and Involuntary Resettlement Due Diligence Report for Dhaka Region Roads (Savar Upazila-W03)
67 Initial Environmental Examination for Dhaka Region Roads (Gazipur City Corporation-W-01)
68 Initial Environmental Examination for Dhaka Region Roads (Savar Upazila-W-01)
69 Initial Environmental Examination for Dhaka Region Roads (Rupganj Upazila-W02)
70 Initial Environmental Examination for Dhaka Region Roads (Rupganj Upazila-W-01)
71 Initial Environmental Examination for Dhaka Region Roads (Savar Upazila-W-02-Part-B)
72 Initial Environmental Examination for Dhaka Region Roads (Savar Upazila-W-02-Part-A)
73 Land Acquisition and Involuntary Resettlement Due Diligence Report for Dhaka Region Roads (Savar Upazila-W-02)
74 Initial Environmental Examination for Dhaka Region Roads (Gazipur City Corporation-W-02)
75 Land Acquisition and Involuntary Resettlement Due Diligence Report for Dhaka Region Roads (Araihazar Upazila-W-02)
76 Land Acquisition and Involuntary Resettlement Due Diligence Report for Dhaka Region Roads (Rupganj Upazila-W-02)
77 Initial Environmental Examination for Dhaka Region Roads (Araihazar Upazila-W02-Part-B)
78 Initial Environmental Examination for Dhaka Region Roads (Araihazar Upazila-W02-Part-A)
79 Land Acquisition and Involuntary Resettlement Due Diligence Report for Gazipur City Corporation (W-01)
80 Land Acquisition and Involuntary Resettlement Due Diligence Report for Gazipur City Corporation(W-02)
81 Land Acquisition and Involuntary Resettlement Due Diligence Report_Savar Upazila_W-01
82 IEE - Narayanganj Roads (Araihazar)
83 IEE- Manikganj Drainage Subproject
84 Comprehensive Solid Waste Management Planning and Small Works (Composting Plant) for Khulna City Corporation
85 Environmental Assessment and Review Framework
86 Resettlement Plan
87 Resettlement Framework
88 Land Acquisition and Involuntary Resettlement Due Diligence Report: Manikganj Khal Re-excavation and Development Subproject
89 Land Acquisition and Involuntary Resettlement Due Diligence Report: Rupganj Road and Drainage Subproject
90 Land Acquisition and Involuntary Resettlement Due Diligence Report: Araihazar Road and Drainage Subproject
At a Glance
Short Title: CRDP-2
Ministry: LGRD
Executing Agency: LGED
Approval Ref:
Project Code: 224261600
Sector: Urban
Status: Ongoing Investment Project
Funded By: ADB.
Budget (Lac): 186700.00
Start Date: Jan-2019
Completion Date: Dec-2025
Name of PD: Md. Hamidul Hoque