Sl. No. Name of the Components Physical Quantity(nos/km/m.) Cost as per DPP (Tk in Lakh) 1 2 3 4 A. Revenue Component : 1. Manpower 15 persons 415.00 2. Supply & Services and Repairs, Maintenance & Rehabilitation LS 419.00 B. Capital Component : 3. Transport (Computer & Furniture.) LS nos 20.00 4. Site Development 876 UP Tk 1752.00 lakh 5. Construction of UP Complex Bhaban(new) 700 Nos Tk. 48230.00 lakh 6. Construction of UP Complex Bhaban( transferred from 1st phase) 176 Nos Tk.12672.00 lakh 7. Construction of incomplete UPs transferred from 1st Phase 246 Nos Tk. 9826.00 8. Payments of 100% Completed UP at 1st Phase 49 Nos. Tk.488.12 lakh 9. Construction of UP Complex Internal Road 131.40 Km Tk. 3639.78 lakh
10. Physical Contingency LS Tk. 300.00
11. Price Contingency LS Tk. 246.30