Important Rural Infrastructure Development Project on Priority Basis (IRIDP-2)

Components


The targets of major components of theproject are indicated below :


 































1.Improvement of Upazila Road(UZR)


465.91 km


2.Improvement of Union Road


1430.07 km


3.Improvement of Village Road


6173.55 km


4.Structure on UZR


1109.32 m


5.Structure on Other Road


14254.39 m


6.Maintenance of Rural Road


4596.91 km


7.Maintenance of Rural Road Structures


1462.06 m


8. Development  of Rural Market


111 nos


9.Boat landing Ghat


64 nos

At a Glance
Short Title: IRIDP-2
Ministry: LGRD
Executing Agency: LGED
Approval Ref: 20.00.0000.412. 06.061.15-74
Project Code: 5143
Sector: Rural
Status: Ongoing Investment Project
Funded By:
Budget: 607644.00
Start Date: Jul-2015
Completion Date: Jun-2021
Name of PD: Md. Shafiqur Rahman