(ANNUAL WORK PLAN) CHAK-2018-19
* Name of the Project Name: Sustainable Small Scale Water Resources Development Project (SSSWRDP)
* Project Period t October'2017 to December'2023.
* Approved Project Cost (In Lac Taka) t Total: 49890.68 GOB 49890.68      PA 0.00
* Cumulative Expenditure up to June'2018 (Taka in Lac) Total: 0.00 GOB 0.00      PA 0.00
* ADP Budget/Allocation FY: 2018-19 (Taka in Lac) Total: 100.00 GOB 100.00      PA 0.00
* The project is scheduled for completion of this year : Yes No√
* The project will be completed in this financial year Yes No√
* Revised ADP allocation will be required to increase / decrease Yes√ No
Name of Components Total Target
Physical Target
 (No, Meter, Km. MM)
Financial Target
(Taka in Lac)
Total BDT
1 2 3 4
A) Revenue Components: t      
1.  Salary  1272 M.M.    
2.. Allowances 1273 M.M.    
3. Supply & Services       
  a) Office Management L.S    
  b) NGO Facilator 30 M.M.    
  b) WMCA  751 M.M.    
  c) Training 76181 T.D    
  d) Consultant 80 M.M.    
  e)  Survey
( PRA/FSDD/DS )
     
 4. Maintenance & Operation: L.S    
Total Revenue: (A) 0.00    
(Kha) Capital Components:      
5. Collection and purchase of resources      
Ka) Jeep 1 No.    
Kha) Pick up      
Ka) Motorcycle      
Gha) Engineering and office equipment L.S    
Eo) Sheet Pile Purchase      
6. Land Acquisition      
7. Civil Works (Sub-project) 75 Nos. (Carried over of the previous years)    
8. CD/VAT      
9. Cost Escalation      
10. Physical Contingency      
Sub-Total (Kha) : 0.00    
Grand Total (Ka+Kha) : 100%